0001 | - | F | Rel-4 | 4.0.0 | 4.1.0 | Corrections on UMTS and combined UMTS/GSM measurements | SP-13 | SP-010468 | approved | S5 | S5-22 | S5-010542 | Agreed | 2001-09-07 | OAMPM | 0 | - |
0002 | - | F | Rel-4 | 4.1.0 | 4.2.0 | Correction of the measured object class for some SGSN MM measurement definitions | SP-15 | SP-020026 | approved | S5 | S5-26 | S5-020212 | Agreed | 2002-03-01 | OAMPM | 0 | - |
0003 | - | F | Rel-5 | 4.2.0 | - | Introduction of ""Performance Measurements Definition Process"" describing the repeatable, top-down process to define measurements for inclusion in future 3GPP Releases | SP-15 | SP-020027 | withdrawn | S5 | S5-26 | S5-020213 | Agreed | 2002-03-01 | OAMPM | 0 | - |
0003 | - | D | Rel-5 | 4.2.0 | - | Introduction of ""Performance Measurements Definition Process"" describing the repeatable, top-down process to define measurements for inclusion in future 3GPP Releases | SP-15 | SP-020167 | rejected | S5 | S5-26 | S5-020213 | Agreed | 2002-03-01 | OAMPM | Concern over wording of scope of new annex. S5 to readdress. | - |
0003 | 2 | F | Rel-5 | 4.2.0 | 5.0.0 | Introduction of ""Performance Measurements Definition Process"" describing the repeatable, top-down process to define measurements for inclusion in future 3GPP Releases | SP-16 | SP-020291 | approved | S5 | S5-28 | S5-028137 | Agreed | 2002-05-24 | OAMPM | - | - |
0004 | - | B | Rel-5 | 4.2.0 | 5.0.0 | Adding performance measurement definitions related to GGSN | SP-16 | SP-020291 | approved | S5 | S5-28 | S5-028120 | Agreed | 2002-05-24 | OAMPM | Apprvd @ SP-16. Accidentally not implemeted in v5.0.0. Later (2002-08-21) withdrawn by S5 due to ""technical incoherence"". SP-17 reinstated the approval. | - |
0005 | - | B | Rel-5 | 4.2.0 | 5.0.0 | Introduction of an optional “Purpose” clause in the measurement template | SP-16 | SP-020291 | approved | S5 | S5-28 | S5-028142 | Agreed | 2002-05-24 | OAMPM | Apprvd @ SP-16. Accidentally not implemeted in v5.0.0. Later (2002-08-21) withdrawn by S5 due to ""technical incoherence"". SP-17 reinstated the approval. | - |
0006 | - | D | Rel-5 | 4.2.0 | 5.0.0 | Addition of explanatory text for Radio Access Bearer (RAB) measurements | SP-16 | SP-020291 | approved | S5 | S5-28 | S5-028141 | Agreed | 2002-05-24 | OAMPM | Apprvd @ SP-16. Accidentally not implemeted in v5.0.0. Later (2002-08-21) withdrawn by S5 due to ""technical incoherence"". SP-17 reinstated the approval. | - |
0007 | - | B | Rel-5 | 5.0.0 | - | Add Performance Measurement (PM) definitions related to GGSN | SP-17 | SP-020503 | withdrawn | S5 | S5-30 | S5-028308 | Agreed | 2002-08-23 | OAMPM | - | - |
0008 | - | B | Rel-5 | 5.0.0 | - | Add an optional “Purpose” clause in the measurement template | SP-17 | SP-020503 | withdrawn | S5 | S5-30 | S5-028309 | Agreed | 2002-08-23 | OAMPM | - | - |
0009 | - | B | Rel-5 | 5.0.0 | - | Introduction of Service Based Performance Measurement Definitions | SP-17 | SP-020503 | revised | S5 | S5-30 | S5-028333 | Agreed | 2002-08-30 | OAMPM | to SP-020609 | - |
0009 | - | B | Rel-5 | 5.0.0 | 5.1.0 | Introduction of Service Based Performance Measurement Definitions | SP-17 | SP-020609 | approved | S5 | - | - | - | 2002-09-10 | OAMPM | from SP-020503 | - |
0010 | - | C | Rel-5 | 5.0.0 | - | Add flexibility in the measurement template for the Measured Object Class (MOC) | SP-17 | SP-020503 | revised | S5 | S5-30 | S5-028335 | Agreed | 2002-08-23 | OAMPM | to SP-020609 | - |
0010 | - | C | Rel-5 | 5.0.0 | 5.1.0 | Add flexibility in the measurement template for the Measured Object Class (MOC) | SP-17 | SP-020609 | approved | S5 | - | - | - | 2002-09-10 | OAMPM | from SP-020503 | - |
0011 | - | F | Rel-4 | 4.2.1 | 4.3.0 | Correction of the subscriber number measurement definitions | SP-19 | SP-030146 | approved | S5 | S5-33 | S5-038142 | Agreed | 2003-02-28 | OAMPM | - | 2003-03-11 |
0012 | - | A | Rel-5 | 5.1.0 | 5.2.0 | Correction of the subscriber number measurement definitions | SP-19 | SP-030146 | approved | S5 | S5-33 | S5-038141 | Agreed | 2003-02-28 | OAMPM | - | 2003-03-12 |
0013 | - | F | Rel-4 | 4.3.0 | 4.4.0 | Correction of the definition of the successful GPRS attach counters | SP-20 | SP-030292 | approved | S5 | S5-34 | S5-038340 | Agreed | 2003-05-23 | OAMPM | - | 2003-06-02 |
0014 | - | A | Rel-5 | 5.2.0 | 5.3.0 | Correction of the definition of the successful GPRS attach counters | SP-20 | SP-030292 | approved | S5 | S5-34 | S5-038339 | Agreed | 2003-05-23 | OAMPM | - | 2003-06-02 |
0015 | - | F | Rel-5 | 5.2.0 | 5.3.0 | Deletion of dual clause 4.1.2 | SP-20 | SP-030292 | approved | S5 | S5-34 | S5-038342 | Agreed | 2003-05-23 | OAMPM | - | 2003-06-02 |
0016 | - | C | Rel-6 | 5.2.0 | 6.0.0 | Addition of GPRS per cause measurement definitions | SP-20 | SP-030293 | approved | S5 | S5-34 | S5-038244 | Agreed | 2003-05-23 | OAMPM | - | 2003-06-02 |
0017 | - | B | Rel-6 | 5.2.0 | 6.0.0 | Introduction of MMS Service Based Performance Measurement | SP-20 | SP-030293 | approved | S5 | S5-34 | S5-038346 | Agreed | 2003-05-23 | OAMPM | - | 2003-06-02 |
0018 | - | F | Rel-4 | 4.4.0 | 4.5.0 | Correction of collection method for SGSN measurements | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038552 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0019 | - | A | Rel-5 | 5.3.0 | 5.4.0 | Correction of collection method for SGSN measurements | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038553 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0020 | - | A | Rel-6 | 6.0.0 | 6.1.0 | Correction of collection method for SGSN measurements | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038554 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0021 | - | F | Rel-4 | 4.4.0 | 4.5.0 | Correction of “outgoing intra-cell hard handovers measurements” | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038556 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0022 | - | A | Rel-5 | 5.3.0 | 5.4.0 | Correction of “outgoing intra-cell hard handovers measurements” | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038557 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0023 | - | A | Rel-6 | 6.0.0 | 6.1.0 | Correction of “outgoing intra-cell hard handovers measurements” | SP-21 | SP-030431 | approved | S5 | S5-35 | S5-038558 | Agreed | 2003-09-05 | OAMPM | - | 2003-09-12 |
0024 | - | F | Rel-5 | 5.4.0 | 5.5.0 | Correction of terms used for subcounter definitions | SP-22 | SP-030645 | approved | S5 | S5-36 | S5-038802 | Agreed | 2003-11-21 | OAMPM | - | 2004-01-05 |
0025 | - | A | Rel-6 | 6.1.0 | 6.2.0 | Correction of terms used for subcounter definitions | SP-22 | SP-030645 | approved | S5 | S5-36 | S5-038803 | Agreed | 2003-11-21 | OAMPM | - | 2004-01-05 |
0026 | - | F | Rel-4 | 4.5.0 | 4.6.0 | Correction of “Radio link addition” measurements | SP-23 | SP-040134 | approved | S5 | S5-37 | S5-048188 | Agreed | 2004-02-27 | OAMPM | - | 2004-03-05 |
0027 | - | A | Rel-5 | 5.5.0 | 5.6.0 | Correction of “Radio link addition” measurements | SP-23 | SP-040134 | approved | S5 | S5-37 | S5-048189 | Agreed | 2004-02-27 | OAMPM | - | 2004-03-05 |
0028 | - | A | Rel-6 | 6.2.0 | 6.3.0 | Correction of “Radio link addition” measurements | SP-23 | SP-040134 | approved | S5 | S5-37 | S5-048190 | Agreed | 2004-02-27 | OAMPM | - | 2004-03-05 |
0029 | - | B | Rel-6 | 6.2.0 | 6.3.0 | Add the measurements about Iu connection release | SP-23 | SP-040135 | approved | S5 | S5-37 | S5-048191 | Agreed | 2004-02-27 | OAMPM | - | 2004-03-05 |
0030 | - | F | Rel-4 | 4.6.0 | 4.7.0 | Correction of “Inter-RAT handover” measurements | SP-24 | SP-040266 | approved | S5 | S5-38 | S5-048462 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0031 | - | A | Rel-5 | 5.6.0 | 5.7.0 | Correction of “Inter-RAT handover” measurements | SP-24 | SP-040266 | approved | S5 | S5-38 | S5-048463 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0032 | - | A | Rel-6 | 6.3.0 | 6.4.0 | Correction of “Inter-RAT handover” measurements | SP-24 | SP-040266 | approved | S5 | S5-38 | S5-048464 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0033 | - | F | Rel-4 | 4.6.0 | 4.7.0 | Correction of “RAB assignment” measurements | SP-24 | SP-040267 | approved | S5 | S5-38 | S5-048465 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0034 | - | A | Rel-5 | 5.6.0 | 5.7.0 | Correction of “RAB assignment” measurements | SP-24 | SP-040267 | approved | S5 | S5-38 | S5-048466 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0035 | - | B | Rel-6 | 6.3.0 | 6.4.0 | Correction of “RAB assignment” measurements | SP-24 | SP-040267 | approved | S5 | S5-38 | S5-048476 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0036 | - | F | Rel-4 | 4.6.0 | 4.7.0 | Correction of “hard handover” measurement definitions | SP-24 | SP-040269 | approved | S5 | S5-38 | S5-048468 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0037 | - | A | Rel-5 | 5.6.0 | 5.7.0 | Correction of “hard handover” measurement definitions | SP-24 | SP-040269 | approved | S5 | S5-38 | S5-048469 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0038 | - | A | Rel-6 | 6.3.0 | 6.4.0 | Correction of “hard handover” measurement definitions | SP-24 | SP-040269 | approved | S5 | S5-38 | S5-048470 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0039 | - | B | Rel-6 | 6.3.0 | 6.4.0 | Addition of the measurements about RAB modification and RAB release by CN | SP-24 | SP-040270 | approved | S5 | S5-38 | S5-048477 | Agreed | 2004-05-14 | OAM-PM | - | 2004-05-28 |
0040 | - | D | Rel-6 | 6.4.0 | 6.5.0 | Restructure clauses 5 and 6 to follow the style of other clauses related to UTRAN measurements for extensibility | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048739 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0041 | - | B | Rel-6 | 6.4.0 | 6.5.0 | Add measurements about Mobility Management | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048656 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0042 | - | B | Rel-6 | 6.4.0 | 6.5.0 | Add mesurements about “PDP context activation procedures initiated by Network” | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048658 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0043 | - | B | Rel-6 | 6.4.0 | 6.5.0 | Add measurements about relocation | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048655 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0044 | - | C | Rel-6 | 6.4.0 | 6.5.0 | Change of the mesurements about “SRNS Relocation” | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048740 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0045 | - | C | Rel-6 | 6.4.0 | 6.5.0 | Split measurements about successful PDP context deactivation | SP-25 | SP-040574 | approved | S5 | S5-39 | S5-048741 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0046 | - | F | Rel-4 | 4.7.0 | 4.8.0 | Correction of “Mobility Management” GPRS attach measurement definitions | SP-25 | SP-040575 | approved | S5 | S5-39 | S5-048563 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0047 | - | A | Rel-5 | 5.7.0 | 5.8.0 | Correction of “Mobility Management” GPRS attach measurement definitions | SP-25 | SP-040575 | approved | S5 | S5-39 | S5-048565 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0048 | - | A | Rel-6 | 6.4.0 | 6.5.0 | Correction of “Mobility Management” GPRS attach measurement definitions | SP-25 | SP-040575 | approved | S5 | S5-39 | S5-048568 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0049 | - | F | Rel-5 | 5.7.0 | - | Correction of measurement about “Failed PDP context activation procedures initiated by Network” | SP-25 | SP-040576 | rejected | S5 | S5-39 | S5-048742 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0050 | - | A | Rel-6 | 6.4.0 | - | Correction of measurement about “Failed PDP context activation procedures initiated by Network” | SP-25 | SP-040576 | rejected | S5 | S5-39 | S5-048743 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0051 | - | F | Rel-4 | 4.7.0 | - | Add missing Measurement Name Length constraints | SP-25 | SP-040577 | rejected | S5 | S5-39 | S5-048746 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0052 | - | F | Rel-5 | 5.7.0 | 5.8.0 | Add missing Measurement Name Length constraints | SP-25 | SP-040577 | approved | S5 | S5-39 | S5-048747 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0053 | - | A | Rel-6 | 6.4.0 | 6.5.0 | Add missing Measurement Name Length constraints | SP-25 | SP-040577 | approved | S5 | S5-39 | S5-048748 | Agreed | 2004-08-20 | OAM-PM | - | 2004-09-13 |
0054 | - | F | Rel-4 | 4.8.0 | 4.9.0 | Correct measurements about GPRS Update Locations sent to the HLR | SP-26 | SP-040783 | approved | S5 | S5-40 | S5-049037 | Agreed | 2004-11-20 | OAM-PM | - | 2004-11-25 |
0055 | - | A | Rel-5 | 5.8.0 | 5.9.0 | Correct measurements about GPRS Update Locations sent to the HLR | SP-26 | SP-040783 | approved | S5 | S5-40 | S5-049038 | Agreed | 2004-11-20 | OAM-PM | - | 2004-11-25 |
0056 | - | A | Rel-6 | 6.5.0 | 6.6.0 | Correct measurements about GPRS Update Locations sent to the HLR | SP-26 | SP-040783 | approved | S5 | S5-40 | S5-049039 | Agreed | 2004-11-20 | OAM-PM | - | 2004-11-25 |
0057 | - | F | Rel-4 | 4.9.0 | 4.10.0 | Correction of measurements on Number of GTP data packets sent and received on the Gn interface | SP-27 | SP-050040 | approved | S5 | S5-41 | S5-058142 | Agreed | 2005-01-28 | OAM-PM | - | 2005-02-07 |
0058 | - | A | Rel-5 | 5.9.0 | 5.10.0 | Correction of measurements on Number of GTP data packets sent and received on the Gn interface | SP-27 | SP-050040 | approved | S5 | S5-41 | S5-058143 | Agreed | 2005-01-28 | OAM-PM | - | 2005-02-07 |
0059 | - | A | Rel-6 | 6.6.0 | 6.7.0 | Correction of measurements on Number of GTP data packets sent and received on the Gn interface | SP-27 | SP-050040 | approved | S5 | S5-41 | S5-058144 | Agreed | 2005-01-28 | OAM-PM | - | 2005-02-07 |
0060 | - | B | Rel-6 | 6.6.0 | 6.7.0 | Add measurements on Number of GTP data packets sent and received on the Gn interface, from SGSN to SGSN | SP-27 | SP-050040 | approved | S5 | S5-41 | S5-058145 | Agreed | 2005-01-28 | OAM-PM | - | 2005-02-07 |
0061 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Correction of measurement type name to RAB.SuccRelPSNoQueuing | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058351 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0062 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing GSM SGSN measurements for subscribers state | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058386 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0063 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing SGSN measurements for GSM ciphering procedures | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058390 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0064 | - | F | Rel-5 | 5.10.0 | 5.11.0 | Correct inter-RAT handover measurement object class UtranRelation to GsmRelation | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058442 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0065 | - | A | Rel-6 | 6.7.0 | 6.8.0 | Correct inter-RAT handover measurement object class UtranRelation to GsmRelation | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058443 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0066 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing UMTS/GSM SGSN measurements for IMEI checking | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058445 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0067 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing UMTS/GSM SGSN measurements for failed PS paging procedures | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058446 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0068 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing GSM SGSN measurements for LLC protocol and SNDCP protocol | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058447 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0069 | - | F | Rel-6 | 6.7.0 | 6.8.0 | Add missing SGSN/GGSN measurements for max number of subscribers | SP-28 | SP-050293 | approved | S5 | S5-42 | S5-058448 | Agreed | 2005-05-13 | OAM-PM | - | 2005-05-25 |
0070 | - | F | Rel-5 | 5.11.0 | 5.12.0 | Correct succeful inter-SGSN Routing Area update procedures | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058835 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0071 | - | A | Rel-6 | 6.8.0 | 6.9.0 | Correct succeful inter-SGSN Routing Area update procedures | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058836 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0072 | - | F | Rel-5 | 5.11.0 | 5.12.0 | Delete wrongly defined Measurements about ”Intra-Cell Hard handover” | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058840 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0073 | - | A | Rel-6 | 6.8.0 | 6.9.0 | Delete wrongly defined Measurements about ”Intra-Cell Hard handover” | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058841 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0074 | - | F | Rel-5 | 5.11.0 | 5.12.0 | Correct incoherent SHO prefixed FDD/TDD radio link management measurements | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058842 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0075 | - | A | Rel-6 | 6.8.0 | 6.9.0 | Correct incoherent SHO prefixed FDD/TDD radio link management measurements | SP-29 | SP-050451 | approved | S5 | S5-43 | S5-058843 | Agreed | 2005-09-02 | OAM-PM | Rel-5 OAM-PM | 2005-09-15 |
0076 | - | F | Rel-6 | 6.8.0 | 6.9.0 | Inconsistent description on the scope of measurements types | SP-29 | SP-050460 | approved | S5 | S5-43 | S5-058837 | Agreed | 2005-09-02 | OAM-PM | Rel-6 OAM-PM | 2005-09-15 |
0077 | - | F | Rel-6 | 6.8.0 | 6.9.0 | Remove ambiguity in 'Successful UMTS PS paging procedures' | SP-29 | SP-050460 | approved | S5 | S5-43 | S5-058839 | Agreed | 2005-09-02 | OAM-PM | Rel-6 OAM-PM | 2005-09-15 |
0078 | - | B | Rel-7 | 6.8.0 | 7.0.0 | Add UTRAN TDD Dynamic Channel Allocation (DCA) counters for Performance Measurement (PM) | SP-29 | SP-050454 | approved | S5 | S5-43 | S5-058740 | Agreed | 2005-09-02 | OAM7-PM-TDD | Rel-7 OAM7-PM | 2005-09-15 |
0079 | - | B | Rel-7 | 6.8.0 | 7.0.0 | Add TDD code resource counters for PM | SP-29 | SP-050454 | approved | S5 | S5-43 | S5-058844 | Agreed | 2005-09-02 | OAM7-PM-TDD | Rel-7 OAM7-PM | 2005-09-15 |
0080 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add TDD Radio Frequency Power counters for PM | SP-30 | SP-050727 | approved | S5 | S5-44 | S5-059123 | Agreed | 2005-11-11 | OAM7-PM | - | 2005-11-23 |
0081 | - | F | Rel-7 | 7.0.0 | 7.1.0 | Correction for TDD Code Counters for PM | SP-30 | SP-050727 | approved | S5 | S5-44 | S5-059124 | Agreed | 2005-11-11 | OAM7-PM | - | 2005-11-23 |
0082 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add DNS query measurements into 3GPP specifications. | SP-30 | SP-050704 | approved | S5 | S5-44 | S5-059128 | Agreed | 2005-11-11 | OAM-PM | - | 2005-11-23 |
0083 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add AAA authentication measurements into 3GPP specifications. | SP-30 | SP-050704 | approved | S5 | S5-44 | S5-059129 | Agreed | 2005-11-11 | OAM-PM | - | 2005-11-23 |
0084 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add periodic RA update measurements into 3GPP specifications. | SP-30 | SP-050704 | approved | S5 | S5-44 | S5-059130 | Agreed | 2005-11-11 | OAM-PM | - | 2005-11-23 |
0085 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add failed RA update per cause measurements into 3GPP specifications. | SP-30 | SP-050704 | approved | S5 | S5-44 | S5-059131 | Agreed | 2005-11-11 | OAM-PM | - | 2005-11-23 |
0086 | - | B | Rel-7 | 7.0.0 | 7.1.0 | Add UTRAN cell carrier RF loading PM measurements | SP-30 | SP-050727 | approved | S5 | S5-44 | S5-059138 | Agreed | 2005-11-11 | OAM7-PM | - | 2005-11-23 |